Cleanup Activities
Start Date | EPA Funding | Completion Date | CA | Accomplishment Counted? | Cleanup Documentation |
01/19/2016 | $9,602.02 | 09/27/2019 | Oklahoma Department of Environmental Quality | No | |
Cleanup/Treatment Implemented:
Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Soil was removed and clay caps were also installed in some areas. A protective barrier lining in the on-site lake was installed to prevent contaminates from entering the surface water. Institutional controls were used to restrict groundwater use.
Address of Data Source:
https://www.deq.ok.gov/land-protection-division/institutional-controls-web-viewer/
Total ACRES Cleaned Up: 40
Number of Cleanup Jobs Leveraged: 0
EPA Cleanup Funding: $9,602.02
Leveraged Funding:
Cost Share Funding:
Total Funding: $9,602.02
Top of Page